Highway Department Update
UPDATES FROM THE CONWAY HIGHWAY DEPARTMENT
We are updating our ongoing road work efforts from the storm. As of September 10th, 2023 , the Highway Department repaired washed out areas on:
Main Poland Rd
Adams Rd
Riley Rd
Since July 4, 2023, Storm, the Highway Department has used 3300 yards of gravel, 800 tons of rip rap and 420 hours of overtime worked. This does not include the work that MASSDOT has provided for Whately Rd, North Poland Rd, Main Poland Rd, Williamsburg Rd and South Ashfield Rd.
THANK YOU MASSDOT!
Posted: to General News on Tue, Sep 19, 2023
Updated: Tue, Sep 19, 2023